Data Centre Migrations - Part 4

Well, the Data Centre is now up and running having gained practical completion last week. As always there are still some bits and pieces to do , such as finish the CCTV, finish the Access Control, finish the EMS and get the generator installed as and when it arrives, but it is now fit to start installing equipment.

This weekend, past saw the arrival of the first few departments from the old building arrive into their shiny new offices, and we have migrated a few of the core services across such as the Vudyo platform, the email service and one of our operating countries.

BT as always are holding us up although they have delivered the ISDN services and a short-haul data service to allow us to start the migration. As like most BT clients we are struggling with our SIP trunks from BT to allow us to get on with the migration to VOIP, but we keep hitting them anyway.

I am looking forward to the postmortem and lessons learned exercise that I am sure will follow this project.

On a different note, I am off to Kuwait early in June to talk at the first ever Kuwait Data Centre conference so that will be interesting, and I have lined up some additional work with Gamma Telecom, one of the UK's leading independent Telecommunications providers

Wednesday, 17 April 2013

Migration Projects - Part 3

Well, we are getting there. The Data Centre is on line, critical systems in place and running on test load at the moment. As always there are a number of small annoying things to finish as part of the tidy up but we are on programme, which is good.

Sadly, the telecommunications phase is holding us up. Good old BT can't get circuits in on time as usual and indeed only starting provisioning the first Short Haul circuit yesterday (17th April). I am, hoping fervently that as soon as that is active we can at least start to migrate and test some of the systems.

When BT actually get moving they are OK. When they finally got round to it we got the fibre sub-ducts in quickly. when they finally got round to it we had the fibre blown in quickly. Their main problem seems to be a complete lack of joined-up management, not helped by the onerous rules that OfCom in the UK subject them too.

Ah well at least us falling behind the curve has taken the bad look off the fact that the office build and fit-out project, being managed by others, is well behind time.

This week and next week could be interesting!

Thursday, 4 April 2013

Migration Projects - Part 2

Well we are still on track.......just!!!!!!

Surprisingly BT have gone from using the slightest excuse not to deliver, to falling over themselves to help. it is surprising what an annual spend in excess of a million bucks does, although, having said that we still have no comms into the building.

We had a nightmare during a power isolation phase when trying to install a new Automatic Mains Failure panel to both split the incoming supply and control the generator. The panel was too big to fit into the available space so we had to cancel and reconfigure the panel to fit. We will have another attempt on Monday night and hopefully get some power into the secure space.

APC as always have let us down. They were supposed to deliver the UPS devices on Monday of this week but decided that they had a fault in the unit and can't now ship until Wednesday next. This is really strange as they were prepared to deliver them a week early but we asked them to hold them back a week as we weren't ready for them. Methinks that someone with a bigger cheque book has paid APC to give them ours.

Still next week is when it all hopefully comes together. BT on site, Power guys on site, UPS on site and cablers on site.

Onwards and Upwards!!!


Friday, 22 March 2013

Migration Projects

While it is nice to be back in some kind of harness after a few months 'enforced' holiday, I am not sure that a complete Data Centre Migration project was the best piece of work to get myself back into. :)

As usual  the company involved, being controlled from the States have taken on a large and complete Data Centre, Systems and 240 people office move, in a three month timescale, into a building that is still be being built.

Very interesting times though and it has been good relearning MS Project, Resource Management and all the various PRINCE 2 type documentation that goes with it.

I have now been at it for ten days solid and surprisingly it is more On Track than Off Track, although as always in these projects we are at the vagaries of the Telecoms provider, in this case BT, to ensure that timely delivery allows us to stage the testing and migration in advance of the personnel move.

All this whilst the organisation provides its 24/7 business service as usual.

Friday, 15 March 2013

Interesting Times

I have just returned from a visit to the Google Data Centre complex in Hamina, Finland. It is possibly the most secure installation I have ever (tried) to set foot in. There are so many layers of security involved it makes all the Data Centres that I have visited, worked in, or been associated with in the past an open shop.

The Hamina centre is the one that uses seawater cooling, dragged in from the Gulf of Finland to their proprietary cooling system. It is an interesting concept, bearing in mind that the salinity levels in that sea are remarkably low, the water being almost brackish, more than salty. I suggest that they get plenty of 'free cooling' too as the sea was completely frozen in during my trip with night-time temperatures of -28degC.

Still and all it was good to see what you can do with a couple of hundred million dollars.

I return to the UK to head up an interim Migration Team for a finance house but somehow I suspect that the facility will not be quite as 'cool'!

Wednesday, 19 December 2012

A Sad Day for the Scottish Data Centre Industry

It was announced today that the juggernaut that is Pulsant has acquired that venerable Scottish Data Centre institution, ScoLocate in an alleged £26 million deal.


Pulsant who are backed by Bridgepoint Development Capital started their buying blitzkrieg with Lumison Ltd, of whom I was an employee, about two years ago, swiftly adding Bluesquare Data then Dedipower to their portfolio. Within a matter of weeks the management of the organisation had been moved to Reading, and to be frank, the heart ripped out of Lumison, a once proud Scottish company.

Following a financial restructuring a couple of years ago, Scolocate were pretty much owned by the Royal Bank of Scotland, whom, as Data Centres were obviously not part of their core business, were eager to sell.

There is obviously money to be made in Data Centres, collocation, managed hosting etc. as it seems that these facilitiess are now being snapped up by people solely interested in short term ownership with sell on profit at the end of the period, and managed by people who have no feel for the industry, or the people who work their.

Whilst all press releases state that the 26 or so people who are employed by Scolocate, which incidentally was another of my jobs from 2000 to 2005, are safe, I somehow sadly doubt that. I fervently hope that they don't rip the heart and soul out of Scolocate too.

That appears only to leave Iomart and to a lesser extent, Brightsolid (formerly Scotland Online) as the last of the true Scottish Data Centres.

Wednesday, 3 October 2012

What Next

Well, as reported in my last post, Pulsant and I are no more. Am I missing it....Not a Jot!!

It has only been a couple of days but just going to bed without my cell phone is a bonus on it's own. No more middle of the night calls for me, at least for a while anyway.

Currently, I am catching up on some house projects which have been booting about for a while, but also talking to a number of people about opportunities as we go.

One of the more exciting concepts is working with Levant UPS who are a fairly new to market concern headed up by Mark Parma. Originally started as a maintenance organisation specialising in MGE devices, they have branched out into build and delivery of cost effective units, which once they are known in the market place, should hopefully give at least Riello and Borri a run for there money.

I am working an initial marketing plan for them at the moment and will keep you posted as to progress.