Well we are still on track.......just!!!!!!

Surprisingly BT have gone from using the slightest excuse not to deliver, to falling over themselves to help. it is surprising what an annual spend in excess of a million bucks does, although, having said that we still have no comms into the building.

We had a nightmare during a power isolation phase when trying to install a new Automatic Mains Failure panel to both split the incoming supply and control the generator. The panel was too big to fit into the available space so we had to cancel and reconfigure the panel to fit. We will have another attempt on Monday night and hopefully get some power into the secure space.

APC as always have let us down. They were supposed to deliver the UPS devices on Monday of this week but decided that they had a fault in the unit and can't now ship until Wednesday next. This is really strange as they were prepared to deliver them a week early but we asked them to hold them back a week as we weren't ready for them. Methinks that someone with a bigger cheque book has paid APC to give them ours.

Still next week is when it all hopefully comes together. BT on site, Power guys on site, UPS on site and cablers on site.

Onwards and Upwards!!!